North Main Street Water Main Replacement

General Project Information / Goals:

The City has experienced a number of water main breaks along the stretch of North Main Street from Llanos Street to the south. This project will replace the old pipe with a new pipe in a different location.  The ultimate goal is to upgrade deteriorated infrastructure.

Project Map

Schedule

Milestone Dates
Start Construction June / July 2021
Completion Late August 2021

Public Information Meeting:

Project staff will hold a virtual Public information meeting on March 3, 2021 via Zoom starting at 5:30pm central time.  Project staff and the design consultant will present the project overview, design concept, and go over the anticipated project schedule. Questions from the public are encouraged.

https://zoom.us/j/95823252418
or by phone
+ 1 312 626 6799
 Webinar ID: 958 2325 2418

https://zoom.us/j/95823252418
or by phone
+ 1 312 626 6799
 Webinar ID: 958 2325 2418


Project Contact

For questions please contact Eric Schulz, Assistant Public Works Director by phone at 608-845-6695 or by e-mail at eric.schulz@ci.verona.wi.us..

Traffic Impacts:

North Main Street will remain open with both directions of traffic being diverted into the northbound lanes. The left turn from southbound Main Street to Llanos will be restricted.

Llanos Street will remain open. The left turn from westbound Llanos Street to Main Street will be restricted. 

North School entrance will remain open. The left turn from the school entrance to Main Street will be restricted.

South School entrance will be closed for the duration of the project